Building management system (BMS)
The real-time control layer — the building's reflexes — that reads sensors and drives actuators (pumps, fans, dampers, breakers) to hold power, cooling, and environment within safe limits second by second. Conservative, industrial software supplied by established automation vendors.
DCIM (Data Center Infrastructure Management)
The awareness and planning layer that aggregates and models information about the whole facility — racks, power provisioned versus drawn, cooling and space available — to support capacity decisions over hours to years, prevent stranded capacity, and translate the facility's state into economic terms.
Facility layer (nervous system)
The physical infrastructure and control software that runs a data center's power, cooling, and monitoring — the 'second machine' that keeps the building alive, distinct from the compute workload it houses. Governed by operational technology and treated in this course as its own intelligence surface.
Liquid cooling (direct-to-chip and immersion)
Cooling methods that bring liquid close to the heat source because liquid carries heat far more effectively than air. Direct-to-chip pipes coolant through cold plates on the hottest components; immersion submerges whole servers in non-conductive fluid. Adopted for high-density compute that air can no longer cool, requiring new facility infrastructure.
Operational technology (OT)
Control systems that sense and act on physical processes — power, cooling, environment — in real time, descended from industrial and building automation. Distinct from information technology (IT), which runs the compute workload. OT prioritizes determinism and safety over features and throughput.
Power Usage Effectiveness (PUE)
A facility efficiency metric: the ratio of total energy drawn by the building to the energy delivered to the compute. A value near 1.1 indicates little overhead; higher values indicate more energy spent on the facility itself, mostly cooling. It measures the building, not the servers.
Redundancy (N, N+1, 2N)
The practice of building spare capacity and parallel paths into power and cooling so no single component's failure stops the flow. N is exactly the required capacity; N+1 adds one spare unit; 2N duplicates the entire path. Greater redundancy absorbs more failure at greater cost.
Stranded capacity
Capacity that physically exists but cannot be sold because a complementary resource is exhausted — for example, power available in a zone whose local cooling is full, or vice versa. Because usable capacity requires power, cooling, and space together, imbalance turns paid-for capacity into lost revenue.