Grid Access and Regulation Foundations
Glossary
- Cluster study
- An interconnection study that evaluates a group of requests together rather than one at a time, required for generators under FERC Order No. 2023 on a first ready, first served basis.
- Interconnection queue
- The ordered list of requests to connect new generators, storage or large loads to the transmission system, each of which must pass engineering studies before an interconnection agreement is signed.
- Large load
- A single customer site with very high electricity demand, typically tens or hundreds of megawatts, such as a data center. Thresholds vary: Texas Senate Bill 6 uses 75 megawatts, while FERC's June 2026 orders proposed 50 megawatts.
- Minimum demand charge
- A tariff provision requiring a customer to pay for a set share of its contracted capacity regardless of actual use, as in AEP Ohio's 85 percent minimum and Dominion Energy Virginia's GS-5 class, which requires 85 percent of contracted transmission and distribution demand and 60 percent of generation demand.
- Moratorium
- A time-limited pause on applications, permits or approvals for a category of development, such as the one-year data center pause adopted by St. Charles, Missouri, in August 2025.
- Public utility commission
- The state agency that regulates retail electricity rates and utility service within a state. Its name varies, for example the Virginia State Corporation Commission or the Public Utilities Commission of Ohio.
- Regional transmission organization
- An independent body that operates the high-voltage transmission system and wholesale electricity market across the territories of many utilities, such as PJM Interconnection or MISO. Independent system operator is a closely related term for the same kind of organization.
- Stranded cost
- Investment a utility has made to serve customers that can no longer be recovered from those customers, for example because a large load leaves early, and that may shift to other ratepayers.